|
Building
the Royal Sovereign Light Tower, Seaford Bay, 1971.
There was a major
construction project at Seaford Bay in 1971 - the Royal Sovereign
Light Tower was built on the beach near Tidemills. The new
tower was built to replace the ninety-six year old light vessel
that marked the dangerous Royal Sovereign rocks off Bexhill.
The new tower was built in two sections designed to be floated
on rafts from the construction site into their final position
at sea. The two sections would be put together on the site
when they arrived. The construction plan went well but when
the day came for the flotation - it didn't work. There had
been some miscalculation and the rafts, even with the help
of the incoming tide, could not shift the great concrete structure
that would be the base of the tower. The builders had to return
to the drawing board. Their re-thinking led to masses of polystyrene
sheets being delivered to the site. These were used to support
the rafts and so gain sufficient floating power to launch
the light tower. It worked, to the delight of many on-lookers,
and the assembling of the new lighthouse went ahead.
One resident of
Newhaven (a member of the Gardening Club) remembers watching
all this going on, and he told me that when it was all over,
lots of large pieces of polystyrene were left floating around
on the sea in Seaford Bay and the local children had a wonderful
time using them as swimming floats.
In 1994 the Royal
Sovereign Light Tower became automatic and solar powered.
Banks of solar panels power a set of lanterns whose light
is visible for 12 miles. Since the Tower is unstaffed there
is also a complicated system involving electronic trip messages
to Harwich when any of the lightbulbs fail.
This is not the
only occasion when large crowds gathered to watch engineering
works near Seaford. On September 19th 1850, people came on
excursion trains from London as well as from nearby to watch
the blasting of part of the cliff at Seaford Head. The idea
was that the chalk and flint that would fall would form a
protective breakwater for the town. Mining engineers carefully
placed seven tons of gunpowder in the cliff face. The plan
worked in that the blast dislodged 200,000 tons of chalk,
but the sea washed most of it away within two decades. In
1881 the sea wall was built to achieve the same purpose.

|